Bags or a truck? The concrete break-even

Nobody can tell you what concrete costs in your town from a web page — pricing swings by region, season, and plant. But you can pin down exactly how much you need before you call anyone, and that number is what decides the whole question.

Start with one number: 45 bags to a yard

A cubic yard is 27 cubic feet. A standard 80-lb bag of concrete mix yields 0.60 cubic feet. Divide and you get 45 bags per cubic yard — the single most useful landmark in bagged concrete, because it tells you instantly when a project has outgrown the bag aisle.

The other yields scale linearly at 0.0075 cubic feet per pound, so 60-lb bags yield 0.45 cubic feet and 40-lb bags yield 0.30.

Cubic yards converted to bags of 40, 60, and 80 lb concrete
Cubic yardsCubic feet40 lb60 lb80 lb
0.256.75231512
0.513.5453023
0.7520.25684534
127906045
1.540.51359068
25418012090
381270180135
5135450300225
10270900600450

Bag counts are rounded up — you cannot buy a third of a bag.

Where bags stop making sense

The break-even is usually quoted as about one cubic yard, and it holds for a reason that has nothing to do with the sticker price: a delivered load carries a minimum and often a short-load charge, so small pours get penalised. Above that, hand-mixing stops being a money question and becomes a logistics one.

Look at what 2 yards actually means. That's 90 bags of 80-lb mix — 7,200 pounds of material loaded into a cart, wheeled to the forms, opened, mixed one batch at a time, and placed before it sets. Concrete doesn't wait, so you can't spread it across two weekends either. Somewhere around 1.5 yards, most people stop pricing bags and start calling plants.

Common slabs, in yards and bags

Net quantities for a rectangular slab, at the three thicknesses that cover nearly every residential pour. Bag figures are 80-lb.

Cubic yards and 80 lb bags for common slab footprints at 4, 5, and 6 inches
SlabSq ft4 in5 in6 in
YdBagsYdBagsYdBags
10 × 101001.25561.7570284
10 × 121201.5672842.25100
12 × 121442802.251002.75120
12 × 161922.510731343.75160
14 × 141962.51093.251373.75164
20 × 2040052236.252787.5334
24 × 245767.25320940010.75480

The formula, so you can check any footprint

cubic feet = length (ft) × width (ft) × thickness (in) ÷ 12

cubic yards = cubic feet ÷ 27

bags = cubic feet ÷ yield (0.60 for an 80-lb bag)

One warning about waste. The concrete calculator reports cubic yards with a 10% waste factor but bag counts without one — a deliberate split, since an extra half-yard in the truck is harmless while unopened bags sit in the garage forever. On a pour you can't redo, buy two extra bags anyway. Running short mid-pour is the one mistake with no recovery.

What a delivered quote actually includes

Delivered pricing can't be quoted from a web page, but the structure of the quote is the same everywhere. Ask for these as separate lines instead of one blended total, and you'll see immediately where the surprises live:

  • Minimum order and short-load charges — the fee that most often makes a small pour surprisingly expensive.
  • Delivery distance — per-mile or zone charges on top of the load.
  • Waiting time — billed once the truck has been on site past a grace period, typically per-yard after a few minutes. Have your help and forms ready before it arrives.
  • Mix design — air entrainment, fibre, accelerators, and higher strengths are add-ons quoted per yard.
  • Cancellation terms — a truck already batched and rolling when you cancel is your cost.

Materials the truck doesn't bring

Concrete is roughly half the job. These are the ones people forget, and unlike prices, the quantities are knowable:

  • Gravel base — 4 inches of compacted crushed stone under the slab. Run your footprint through the gravel calculator rather than guessing; it converts depth directly to tons.
  • Form lumber and stakes — 2×6 or 2×8 for the edge, braced often enough that it can't bulge under the weight of wet concrete.
  • Reinforcement — mesh or rebar, plus the chairs or dobies that hold it at mid-slab depth instead of on the ground where it does nothing.
  • Curing and finishing — a groover for control joints, an edger and float, and either a sealer or a week of keeping the slab damp.

Run your own numbers

The concrete calculator outputs the truck order and the bag count side by side for your exact footprint, thickness, and pour shape. It opens on the 10×12 slab at 4 inches used throughout this guide — 1.5 cubic yards, 67 bags of 80 lb — and flipping the thickness to 6 shows how far the bag column moves before a truck wins. Pouring footings or setting posts instead? The per-post bag chart covers post holes by diameter and depth.

Common questions

Is it cheaper to mix bags or order a ready-mix truck?

Under about 1 cubic yard, bags almost always win — a delivered load carries a minimum order and often a short-load charge, and you can't buy 0.4 of a yard without paying for more. Past roughly 1 yard the truck wins on both money and your back: 2 yards is 90 bags of 80-lb mix, which is 7,200 pounds of material you'd have to carry, open, mix, and place by hand.

How many bags of concrete do I need for a 10×12 slab?

A 10×12 slab at 4 inches is 40 cubic feet — 1.5 cubic yards. In bags that's 67 bags of 80 lb, 89 of 60 lb, or 134 of 40 lb. At 6 inches thick, the same footprint needs 100 bags of 80 lb. Thickness scales the answer linearly, so a 1-inch change moves the bag count by about 17.

What is a short-load fee?

Ready-mix plants price and schedule around full trucks, so a partial load costs them the same dispatch and leaves them selling the remainder at a discount. Many charge a short-load fee on orders below a minimum, and some small plants run dedicated short-load trucks that will deliver a fraction of a yard for a per-yard premium. Ask for the delivered total on your exact volume, not the advertised per-yard rate.

How thick should my slab be?

4 inches for patios and walkways, 5–6 inches for a residential driveway or anything a vehicle crosses. Thickness drives volume almost linearly — a 5-inch slab is 25% more concrete than a 4-inch slab over the same footprint, which is why the thickness decision belongs before the supplier call, not after.

Do I need rebar or just wire mesh?

For 4-inch patios, 6×6 wire mesh or fiber-mixed concrete is common. Driveways and structural slabs should use #4 rebar on 18–24 inch centers, chairs to hold it mid-slab, and proper control joints. When in doubt, follow your local code — this guide is for planning, not engineering.

Quantities assume standard mix yields and a level, rectangular pour. Concrete pricing, minimums, and short-load policies vary by plant and season — get a delivered total in writing for your own volume. For load-bearing or permitted work, consult an engineer.