FIELD GUIDE · CONCRETE

How many bags of concrete for a sonotube?

A tube is the one concrete pour with no post to subtract from the volume. That makes the answer a single multiplication — and the reason most estimates for a 12-inch tube are a bag or two short.

A tube is a cylinder, and nothing else

Fiber concrete forms — Sonotube is the brand name most people use for all of them — are open tubes of fixed diameter that you cut to length and set in the ground. The concrete you pour is the full round volume. There is no post standing in the middle of it, so unlike a fence post hole there is nothing to deduct: what the inside of the tube measures is what you buy mix for.

That is the whole calculation, and it is why the numbers on this page can be checked with a tape measure and one formula. The rest of the guide is the practical part — measuring the right diameter, working out the height you actually pour, and not being short a bag at the bottom of the last lift.

The formula, so you can check the chart

Volume of a cylinder is area of the circle times height. In feet, with the diameter measured in inches:

volume (cu ft) = π × (diameter ÷ 24)² × height (ft)

The 24 is doing two jobs: halving the diameter for the radius, and dividing by 12 to get from inches to feet.

Take the most common size there is, a 12-inch tube three feet tall. Diameter ÷ 24 is 0.5, so the radius squared is 0.25 and the area is 0.785 square feet. Times three feet of height is 2.36 cubic feet. Divide that by the 0.60 cubic feet an 80 lb bag yields and you get 3.93 bags — which rounds up to 4.

That rounding direction is deliberate. Every figure here rounds up, because a footing three percent short of its planned volume is not a footing you can top up later once the mix has started to set.

Chart: bags by tube diameter and height

Heights are the cut length of the tube, not the length printed on it in the store. A 48-inch tube cut down to 30 inches is poured as a 30-inch tube, and that is the row to use.

Concrete bag counts per fiber tube by inside diameter and tube height
Tube dia × heightConcrete (cu ft)40 lb60 lb80 lb
8" × 24"0.70322
8" × 36"1.05432
8" × 48"1.40543
10" × 24"1.09432
10" × 36"1.64643
10" × 48"2.18854
12" × 24"1.57643
12" × 36"2.36864
12" × 48"3.141176
14" × 24"2.14854
14" × 36"3.211186
14" × 48"4.2815108
16" × 24"2.791075
16" × 36"4.1914107
16" × 48"5.59191310
18" × 24"3.531286
18" × 36"5.3018129
18" × 48"7.07241612

These are the numbers the concrete calculator returns for the same tube, rounded up to whole bags. Counts are calculated from the exact volume, not from the rounded column beside them: a 14-inch tube 48 inches tall prints as 4.28 cu ft but the true figure is fractionally over eight bags of 80 lb, so the chart shows 8 rather than 7.

How much tube one bag fills

Working from the other end is often more useful on site. If you have six bags in the truck and need to know whether they will finish the pour, this is the answer: one 80 lb bag is 0.60 cubic feet, so it fills the tube to a fixed height that depends only on diameter.

Height of tube filled by one 80 lb bag of concrete, by tube diameter
Tube diameterHeight per 80 lb bagBags for 48 in
8 in20.6 in3
10 in13.2 in4
12 in9.2 in6
14 in6.7 in8
16 in5.2 in10
18 in4.1 in12

The pattern to notice: doubling the diameter quadruples the concrete per inch of height. An 8-inch tube climbs 20.6 inches on a bag while an 18-inch tube climbs 4.1 — same bag, one fifth the height. That is the single most expensive assumption people make when they size a tube by eye.

Height is a decision, not a product size

Tubes are sold in a few long lengths — 48 inches is the common one at a lumberyard — and cut with any handsaw. What you are deciding when you cut is how much footing you want, and there are three heights in play at once:

  • How deep it is buried. The buried length has to reach below the frost line where the ground freezes, or the footing moves with the season. That depth is set by your region and your local building department, not by a number in a national guide.
  • How high it finishes above grade. Two to four inches is typical for a footing that carries a post or a bracket, and it keeps the base of the wood out of standing water.
  • What the cut length adds up to. Buried depth plus above-grade height is the number to enter in the calculator. A tube in a 3-foot hole finishing 4 inches proud of the ground is poured as 40 inches, not 36.

If the cut length falls between chart rows, use the next row up. A 40-inch pour is sized as 48 inches, because the alternative is being short. On a footing carrying a structural load, the plan or an engineer sets the dimension — this page only tells you how much mix it takes.

Which bag size to buy

The bag sizes are interchangeable in volume, not in effort. Pick the largest bag you can lift and mix comfortably, then buy that size.

Concrete bag sizes, yield, and bags needed per cubic yard
BagYieldBags per cu yd
40 lb0.30 cu ft90
60 lb0.45 cu ft60
80 lb0.60 cu ft45

A cubic yard is 27 cubic feet, which is where the 45 figure for 80 lb bags comes from. That number is the useful tripwire: six tubes at 6 bags each is 36 bags, still in bag territory, but a dozen 18-inch tubes crosses a yard and a half and stops being a wheelbarrow job. Past about a yard, a delivered mix is easier to place and easier to finish before it starts to set — the bags versus ready-mix break-even guide works through where that line falls.

Pouring the tube

The bags are only half the job. The details that decide whether a footing lasts are the ones around the pour:

  • Brace before you pour. A tube full of wet mix is heavy and it will bulge and lean if nothing holds it. Stake it on two adjacent sides and check it with a level on both faces, not one.
  • Fill in lifts and rod each one. Twelve to 18 inches at a time, working a rod or a scrap of rebar up and down through the full depth of the lift to release trapped air. Tapping the outside of the tube helps at the walls.
  • Crown the top away from the post. Slope the finished surface so water runs off rather than sitting against whatever sits on the footing.
  • Check the plan for reinforcement. Many tube footings carry a bar or a small cage. Whether yours does is an engineering question for the plan or your local code, not something to guess from a bag label.
  • Keep heavy loads off it. Concrete gains strength over days, not hours. Setting a post or stacking material the next morning is asking the footing for strength it does not have yet.

Mix to the yield on the bag rather than to a consistency that feels right. A mix that pours like soup has more water in it than the mix designer intended, and water is the thing that costs strength. If a bag feels stiff, more mixing time usually fixes it before more water does.

The mistakes that cost a bag, or a footing

01

Sizing off the outside diameter

The tube wall adds thickness, so the outside measures wider than the hole the concrete fills. Wrap a tape around the tube for the circumference if you need to check it, then divide by pi — or measure across the opening's inside.

02

Forgetting that the buried part still holds concrete

A tube set 12 inches into the ground is poured for its full length, not just the above-grade part. Cutting a 48-inch tube down to 36 and then pouring only 24 inches leaves a footing half the size you planned.

03

Dumping a 48-inch tube in one lift

A single dump traps air against the tube wall, and the voids show up later as honeycomb. Fill in lifts of about 12 to 18 inches and rod each lift through its full depth before adding the next.

04

Adding water until it pours easily

Extra water makes a mix that places faster and cures weaker. Mix to the bag's stated yield, and if it needs to be wetter to work, that is a sign it needs more mixing time rather than more water.

05

Leaving the tube on forever, or stripping it in an hour

Fiber tubes are usually left in place below grade and stripped above grade. Either way, the concrete needs to hold its own shape first — a day at minimum before removing anything, and check the mix's own instructions.

Run your own tube count

The link below opens the concrete calculator in its cylinder mode, on the 12-inch tube 3 feet tall from this page — no post deducted — showing 2.36 cubic feet and 4 bags of 80 lb. Change the diameter and depth to your own tube and the bag counts follow, with the cubic yards shown alongside so you can see the moment the job stops being a bag job.

Setting posts in the ground instead of pouring a footing? Bag counts per fence post is the same arithmetic with the buried post subtracted, and the deck board counts by deck size covers what sits on top of the footing once it has cured.

Common questions

How many bags of concrete for a 10-inch sonotube?

A 10-inch tube 24 inches tall holds about 1.09 cubic feet — 2 bags of 80 lb, 3 of 60 lb, or 4 of 40 lb. The common 48-inch length holds about 2.18 cubic feet, which is 4 bags of 80 lb. Diameter drives the count more than anything else, because the volume grows with the square of it.

How many bags of concrete for a 12-inch sonotube 4 feet tall?

Six bags of 80 lb mix. A 12-inch tube 48 inches tall is 3.14 cubic feet, and each 80 lb bag yields 0.60 cubic feet, so 3.14 divided by 0.60 is 5.24 and rounds up to 6. In 60 lb bags it takes 7, and in 40 lb bags it takes 11.

How much of a sonotube does one 80 lb bag fill?

About 20.6 inches of an 8-inch tube, 13.2 inches of a 10-inch tube, 9.2 inches of a 12-inch tube, 6.7 inches of a 14-inch tube, 5.2 inches of a 16-inch tube, or 4.1 inches of an 18-inch tube. One bag is 0.60 cubic feet of mix, divided by the tube's cross-section — which is why a wide tube climbs so much more slowly.

Do I fill the whole sonotube?

Yes. The concrete is the footing, so it goes the full length of the form, including whatever is buried. The only exception is a tube cut short on purpose — in that case the number to size is the cut length, not the length printed on the tube you bought.

Should I put gravel in the bottom of a sonotube?

It is optional and depends on the ground. A 4 to 6 inch gravel layer under the tube drains water away from the base in wet, heavy soil. In well-drained sand or gravel it mostly just adds depth to dig. If you do add it, set the tube on top of the gravel rather than letting the gravel eat into the tube's length.

Can I pour dry mix into a sonotube?

Only if the bag says it is a fast-setting mix formulated for that. Standard concrete mix has to be mixed with water first, either in a wheelbarrow or in a bucket with a paddle, because dry mix poured into a tube will not get water to the bottom half. Fast-set mixes set within minutes of the water, so the tube has to be braced and checked before you pour.

Volumes assume a straight, round tube of the stated inside diameter and whole bags rounded up. Tubes bulge under the weight of wet mix, especially tall ones, so a deep pour can take slightly more than the chart says. Frost depth, footing size, and reinforcement come from your local building code or an engineer.